Home Improvement and DIY forums

Find answers, ask questions, and connect with DIY and home improvement experts.

Forums Forums SOLAR FORUM UK G99 application offer being less than what’s allowed under G98?

  • G99 application offer being less than what’s allowed under G98?

    Posted by Simon Fielden on March 11, 2026 at 11:24 am

    Has anyone ever heard of a G99 application offer being less than what’s allowed under G98?

    Spen have effectively said to my installer in reply to his G99 application that max export they will allow is 2.6kW however if we install under G98 they effectively can’t limit me to less than 3.68kW!

    I thought the local grid here was under strain especially since there has been about a 50% increase of new houses built down our lane out here in the sticks over the last 20 years, with no reinforcement afaik, but I hadn’t realised it was that bad!

    Not a happy bunny at all

    Warren Hughes replied 1 month ago 10 Members · 12 Replies
  • 12 Replies
  • Terry Norland

    Member
    March 11, 2026 at 11:25 am

    For export? Yes. Happened to a client in 2022/23. And a 3 phase upgrade was needed and took 8 months all told between quote and going live due to DNO not being supper quick doing the upgrade works required.

    Your property is most likely in a village with overhead power cables and what they call, “end of line” from the substation so very very problematic for pushing voltage rises up the chain.

  • Thomas Murphy

    Member
    March 11, 2026 at 11:25 am

    Thanks yep that’s pretty much exactly how our power is deployed here poles all over the shop, probably just over twenty properties on our local transformer hanging off a pole in a nearby field!

    I am about mid way from it and the end of the line

  • Tom Reed

    Member
    March 11, 2026 at 11:26 am

    Yes, we just did a G98. The transformer got upgraded about 6 months later, got a 5+5 through on a fast track once the work was completed.

  • Ula Gasgoine

    Member
    March 11, 2026 at 11:26 am

    Yes. 7.5kw inverter but 0kw export or could do g98 route with 3.68 export. Wouldn’t even allow 7.5kw with export limited to 3.68kw. Northern power grid for reference

    • Simon Fielden

      Member
      March 11, 2026 at 11:27 am

      Yes effectively as best as I can understand I can have a 6kw inverter and 2.6kW export limit under G99 which also allow me to have a gateway

      Or 2x 3.68kW inverters, one or both being export limited via G100 under the G99 fast track process. But I then can’t have a functional gateway i.e. I can have a gateway but it can’t be used for power cut protection!

    • Ula Gasgoine

      Member
      March 11, 2026 at 11:28 am

      The gateway is irrelevant to your export limit.

      I think there may be some miscommunication here.

  • Chris Ward

    Member
    March 11, 2026 at 11:28 am

    Very common for SPEN unfortunately. And they’ll want £300 odd quid plus vat for the privilege.

  • Simon Fielden

    Member
    March 11, 2026 at 11:29 am

    The route I am being offered by the DNO is either a single 6kW inverter and 2.6kW export via full G99 or 2x 3.68kW inverters, G100 export limited to 3.68kW via the G99 fast track process in theory that is great BUT… no islanding via Fastrack so no gateway, that is really annoying because we get lots of brief power cuts here!

  • Will Cooke

    Member
    March 11, 2026 at 11:29 am

    Yes, had this a few years ago. Went down the G98 route, submitted the post installation notification, then instructed us to set export to 0W, due to property being at the end of the line and the network being knackered, requiring reinforcement. DNO then spent over a year trying to get access and wayleaves in place with a landowner. Nightmare PITA job!

  • Willie Baker

    Member
    March 11, 2026 at 11:30 am

    Happened to us recently

    Applied for 6kw inverter

    Came back

    2kw inverter with zero export at a cost of £326.20

    Or

    G98 for no cost

  • Zac Kendall

    Member
    March 11, 2026 at 11:30 am

    Bonkers.

    I imagine your dilemma now is, go big and go after more self usage or stick to the 3.6kW inverter. If you are a high user or are looking at better future proofing your probably better going big with the lesser export

    You may want to look into bring really clever exporting from a slightly oversized battery system

  • Warren Hughes

    Member
    March 11, 2026 at 11:31 am

    “Spen have effectively said to my installer in reply to his G99 application that max export they will allow is 2.6kW however if we install under G98 they effectively can’t limit me to less than 3.68kW! “

    There is a difference, a G99 will allow you to connect a much larger inverter restricted to 2.7kW … that may be useful still for faster battery charging. With a 3.68kW G98 you can only connect a 3.68kW or smaller inverter, not a large one throttled back.

Log in to reply.